CA-7: FY 2006 Performance; 1st Quarter FY 2009 Claims Received and Timeliness; Cumulative FY 2009 Timeliness with Comparison to FY2006
|
Independent Agencies, Bureaus, Commissions, Offices |
FY2006 Timeliness |
FY2009 Target |
1st Qtr Claims |
1st Qtr Timeliness |
FY2009 Cumulative Timeliness |
Cumulative Timeliness vs FY2009 Target |
|
African Development Foundation |
N/A |
60.0% |
0 |
No Claims |
No Claims |
N/A |
|
Agency for International Development |
41.7% |
60.0% |
3 |
33.3% |
33.3% |
-44.4% |
|
American Battle Monuments Commission |
N/A |
60.0% |
0 |
No Claims |
No Claims |
N/A |
-
Department-level performance comprises all relevant agencies and bureaus, including those broken out separately by name.
-
The timeliness percentage indicates the number of CA-7 forms submitted to DOL within 7 calendar days (5 work days) of submission to supervisor compared to all CA-7 forms submitted during the quarter.
-
FY2006 timeliness is not available if individual performance was not reported in that fiscal year.
-
Cumulative timeliness is not available if no claims were filed during FY2009.
-
Cumulative comparison is calculated as follows: [(All FY2009 timely claims / All FY2009 claims) - FY2006] / FY2006
-
Cumulative comparison is not possible if FY2006 or cumulative timeliness is not available.