Skip to page content
Office of Workers' Compensation Programs
Bookmark and Share

Office of Workers' Compensation Programs (OWCP)

EEOICP Program Statistics

Last year, the DEEOIC deployed a new case management system for use by our claims staff. The new system is constructed differently than the previous system, and we determined that it was appropriate to re-examine our statistics and how they are displayed on the web site. For the past several months, we have been working on reconstructing the site and the statistics. Therefore, viewers may notice some differences in the web statistics.

The separate category for the non-covered applications has been removed and those counts are now included in the Final Decision counts. Although the number of posted denials appears to increase, there is not an increase in total numbers. Denials are being shown under a single category instead of being split into two separate counts.

In the past, on our state-by-state pages, medical bill payments were attributed to each state in which any claimant (including multiple survivors) on the case resided, resulting in an overstatement of the amount of medical bill payments in a given state. Medical bill payments are now being attributed to the state in which the employee resides. Although the National page total was not affected by this change, the current state medical totals will show a reduction from previously-reported amounts.

A list of definitions for the terms used on the EEOICP Program Statistics web pages is available here.


LINDE CERAMICS PLANT - NEW YORK
Data as of
Statistical data updated weekly on Mondays

Combined Part B and E Summary
  CLAIMS CASES
Applications Filed 1,301 806 *
Total Compensation Paid - Payments 581 382
Combined Part B and E Dollar Amounts
Total Dollars $54,487,032
Total Medical Bills Paid - Total Dollars $2,384,406
Total Compensation + Medical Bills Paid $56,871,438

* The above numbers of applications filed represent 551 unique individual workers.


Part B
  CLAIMS CASES
Applications Filed 914 531
Final Decisions - Approved 495 298
Final Decisions - Denied 353 220
Final Decisions - Total 848 518
Compensation Paid - Payments 491 297
Part B Compensation Paid
Compensation Paid - Total Dollars $44,550,000

Part E
  CLAIMS CASES
Applications Filed 387 275
Final Decisions - Approved 139 113
Final Decisions - Denied 204 136
Final Decisions - Total 343 249
Compensation Paid - Payments 90 85
Part E Compensation Paid
Compensation Paid - Total Dollars $9,937,032

Part B Cancer Cases - NIOSH Statistics
  CASES
Part B - Status and Location of NIOSH Referrals
Cases Referred to NIOSH for Dose Reconstruction (DR) 344
Cases Returned by NIOSH - With Dose Reconstruction (DR) 226
Cases Returned by NIOSH - Without Dose Reconstruction (DR) *1 111
Cases Returned by NIOSH - Total 337
Cases Currently at NIOSH 7
Part B - Cases with Dose Reconstruction (DR) and Final Decision
Final Decision to Accept and Probability of Causation (POC) 50% or Greater 106
Final Decision to Accept and Probability of Causation (POC) 50% or Greater - Cases Paid 105
Final Decision to Accept and Probability of Causation (POC) 50% or Greater - Individual Claims Paid 165
Final Decision to Accept and Probability of Causation (POC) 50% or Greater - Amount Paid $15,800,000
Final Decision to Deny and POC Less Than 50% 99
Final Decision - Total 205